Pulpmill Stendal (Civil Works) |
Settling the claims (contractor) and counterclaims (employer) after finishing the work on site |
- Screening of the complete, relevant correspondence
- Screening of the minutes of meeting
- Refurbishing of the existing variation orders/offers
- Generating additional variation offers
- Rating the counterclaims
- Working out and negotiating a compromise line
|
6 months |
Central station Berlin (Civil Works) |
Supporting the project team during erection phase |
- Observing and managing the correspondence
- Participating in meetings
- Announcing and canceling notices of obstruction as well as notices of reservation
- Commenting or rejecting delay notifications
- Generating and negotiating variation orders/offers, contract compliant
- Co-ordinating the measuring of realized process
|
10 months |
Power plant Duisburg (Plant construction) |
Settling the claims (contractor) and counterclaims (employer) after finishing the work on site to prepare the final negotiations |
- Refurbishing of the existing supplements
- Generating additional variation orders/offers
- Rating the counterclaims
|
9 months |
New power plant (lignite) Grevenbroich-Neurath (Plant construction)
|
Claim management and contract management on site (during erection and commissioning) |
- Observing and managing the contract-relevant correspondence
- Announcing and canceling the notices of obstruction as well as notices of reservation
- Continuesly comparing the target figures with the actual output (process)
- Generating and negotiating variation orders/offers, contract compliant
|
60 months |
New power plant (anthracite) Hamburg-Moorburg (Plant construction) |
Claim management and contract management on site (during erection and commissioning) |
- Observing and managing the contract-relevant correspondence
- Announcing and canceling the notices of obstruction as well as notices of reservation
- Continuesly comparing the target figures with the actual output (process)
- Generating and negotiating variation orders/offers, contract compliant
|
45 months |
Crossroad Leutzscher Allee Leipzig (Civil works)
|
Variation orders/offers for additional works |
- Identifying and recording the variation orders/offers by comparing the target figures with the actual output
- Creating the variation orders/offers, compliant to the VOB/B
|
1 month |
Modification power plant (lignite) Wilhelmshaven (Plant construction)
|
Claim management and contract management on site (during erection and commissioning) |
- Observing and managing the contract-relevant correspondence
- Announcing and canceling the notices of obstruction as well as notices of reservation
- Continuesly comparing the target figures with the actual output (process)
- Generating and negotiating variation orders/offers, contract compliant
|
12 months |
New production hall including outbuildings Cuxhaven (Civil Works) |
Claim management and contract management on site (during erection and commissioning)
Project management
|
- 1st phase: Generating and negotating variation orders/offers, contract compliant
- 2nd phase: Takeover the overall project management
|
18 months |
New rapid train line Berlin (Railway construction) |
Variation orders/offers for changed works |
- Registering the additional work by comparing the target figures with the actual output
- Generating variation orders/offers, compliant to the VOB/B
|
10 months |
New construction and renovation of a Administration building Berlin (Civil Works) |
Claim management and contract management on site (during erection and commissioning) |
- Observing and managing the contract-relevant correspondence
- Announcing and canceling the notices of obstruction as well as notices of reservation
- Continuesly comparing the target figures with the actual output (process)
- Generating and negotiating variation orders/offers, contract compliant
|
24 months |